Mission Statement:
We are inspired each day when a new or existing customer commits to Frey-Moss by selecting us as their structure provider. A customer chooses to work with Frey-Moss not only because our product is superior and competitive, but also because they know our level of commitment. Our customers want a company that is sincerely looking out for their best interest, is dedicated to continued innovation, and will truly be a long-term partner. This is our focus.
We are committed to growing Frey-Moss into a truly great company. Strong relationships with customers, a top of the line facility and a phenomenal management team have helped this company grow rapidly over the last several years. We are committed to both our customers and co-workers to continue the rate of growth.
To ensure our focus remains on building a great company and servicing the needs of our customers, we have established three fundamental beliefs by which Frey-Moss operates. We believe our integrity, character, and attitude toward work are displayed by these key values:
Deliver Employee Success
We are committed to making this a great place to work. Frey-Moss will be a place where expectations are high and everyone works hard with great passion; those that perform will have tremendous autonomy and will be given the freedom to make a tangible impact on the organization. The environment is fast pace, demanding, and rewarding. The goal is to fill Frey-Moss with bright, passionate, and entrepreneurial people achieving their personal and professional goals.
Deliver Customer Success
We will consistently strive to exceed customer expectations and build long-term relationships. Frey-Moss employees promise to deliver an excellent solution and value proposition to our customer.
Deliver Company Success
We will be an aggressive organization, consistently pushing toward growth and profitability with an increasing impact on the market place.
The Development Process
Click here to contact us now so that we may begin your project!
Step one
- Initial contact with Frey-Moss Structures sales personnel to clarify scope and identify customer requirements, 1-2 days
Step two
- Proposal submitted for customer’s review and identification of scope changes. Upon both parties’ approval, the contract is executed, 1-2 weeks
Step three
- Engineering begins and drawings are submitted for customer approval, 2-4 weeks
Step Four
- Drawings are modified, if necessary, and approved; state approvals are requested, 2-4 weeks in most cases
Step five
- Manufacturing of your modular structure begins. This will vary in length of time depending on the type of structure being built. As the fabrication process starts, your site contractor begins site preparations parallel to that of the building. This includes pouring pier foundations designed by Frey-Moss, ensuring proper building support.
- It is easy to see that with site preparation and building construction happening simultaneously, the time it takes to go from design to an operating business bringing in customers can be reduced as much as 30 days. This dramatic timesaving feature means more money to you and avoidance of costly over runs, which typically happen on most stick built projects.
Step six
- Delivery, installation and completion 1-2 weeks.
- Your brand new store has been built and is now ready for delivery. Our team goes on the road to assist in all operations involved in installing the building. We can deliver to most anywhere in the U.S. Because of the modular design, we are able to transport to your site in a safe and controlled manner.
- At the site, a crane will place each piece in their exact position. The foundations provided by the general contractor are poured to our specifications and this is where our precision planning and construction really pay off. All the pieces fit together much like an erector set with each bolt and each fitting lining up perfectly. Once in place, everything is welded down. Plumbing and electrical hook ups are made by the general contractor. Amazingly, in just one day on the site, your Frey-Moss modular structure is in place.